LRB-4395/1
JTK:kmg:jf
1997 - 1998 LEGISLATURE
February 5, 1998 - Introduced by Senator Burke, cosponsored by Representative
Bock. Referred to Joint committee on Finance.
SB442,1,3 1An Act relating to: the expenditure of $256,744.55 from moneys appropriated
2to the department of transportation for payment of a claim against the state
3made by CleanSoils Wisconsin, Inc.
Analysis by the Legislative Reference Bureau
This bill directs expenditure of $256,744.55 from moneys appropriated to the
department of transportation (DOT) for state highway rehabilitation in payment of
a claim made by CleanSoils Wisconsin, Inc., against DOT. The claimant was a
subcontractor of the general contractor (James Peterson Sons, Inc.,) for a highway
construction project on STH 97 in Marathon County in 1995. The claimant was hired
to clean up soil at a contaminated site. The claimant's work was not completed by
its contractual completion date. The claimant received a change order from the
project's consulting engineers, Central Wisconsin Engineers (another subcontractor
for the general contractor) that authorized a later completion date. DOT asserts that
Central Wisconsin Engineers had no authority to waive the completion date. DOT
also asserts that the claimant's work was not performed in accordance with the
specifications or reasonable professional standards. In late 1995, DOT hired Rust
Environment and Infrastructure, Inc. (consulting engineers), and McNulty Trucking
Company to complete the work begun by the claimant. The claimant was paid
$233,065.45 by the general contractor for work performed. The claimant claimed
$331,581.25 for processing 9,625 tons of soil at $34.45 per ton, plus $38,633.75 for
excavation, stockpiling, backfill and compacting (total = $370,215). After
subtracting the amount that the claimant was paid, this results in a net claim of

$137,149.55. In addition, the claimant claims $175,695 for lost profits. This claim
is based on 5,100 tons of soil processed by Rust Environment and Infrastructure for
which the claimant asserts it would have earned a profit of $23.45 per ton. The
claimant's claim totals $256,744.55. On October 30, 1997, the claims board
recommended denial of a claim of $175,695 by this claimant (see Senate Journal, p.
334).
The people of the state of Wisconsin, represented in senate and assembly, do
enact as follows:
SB442, s. 1 1Section 1. Claim against the state. There is directed to be expended from
2the appropriation under section 20.395 (3) (cq) of the statutes $256,744.55 in
3payment of a claim against the state made by CleanSoils Wisconsin, Inc., Vadnais
4Heights, Minnesota, to compensate it for soil decontamination work performed in
5relation to an improvement project on STH 97 in Marathon County in 1995, plus lost
6profits on work performed by a substitute contractor on the same project who was
7hired by the department of transportation. Acceptance of this payment operates as
8a full and complete release to this state, its officers, employes and agents from any
9further liability to the claimant in connection with this project.
SB442,2,1010 (End)
Loading...
Loading...